SPF Architects creates Obama Sports Complex from pre-engineered metal structures

Architecture studio SPF Architects has completed a sports facility in Los Angeles consisting of two separate buildings that were built using pre-engineered metal structures in order to not disrupt activity at the site.

Originally called the Rancho Cienega Sports Complex, the Michelle and Barack Obama Sports Complex was sited in Baldwin Hills, a neighbourhood in Los Angeles renowned for its athletic achievement.

SPF Architects designed atheletic buildings for the Michelle and Barack Obama Sports Complex

Local architecture studio SPF Architects expanded the existing 29-acre park with new structures that houses basketball and swimming facilities.

Because of the ongoing athletic activity at the park, it was necessary that SPF Architects find a design program that involved multi-phase construction.

Obama sports complex LA exterior
The complex consists of two pre-engineered metal buildings

The studio landed on pre-engineered metal buildings (PEMB) from Nucor in order to create structures spacious enough for athletic activity that could be fabricated off-site.

The PEMBs consist of the structure and an exterior, which consists of insulated rib metal panels.

Ribbed metal facade
The facade was customized by the achitects to include more windows

SPF Architects principal Zoltan Pali said that this particular structure is commonly called a Bulter building.

"When you see these pre-engineered metal buildings, seeing them out on these big giant farm buildings," Zoltan told Dezeen. "It's basically a box – there's very little fenestration on it."

"So for both of them what we did was really modified and altered that significantly," he continued.

Courtyard between the buildings with trees and parking lot
There is a space between the two facilities

These modifications entailed having the metal skin of the exterior not come all the way to the ground so glass panels could be placed there instead, some of which can be lifted up like garage doors, opening the interior to the athletic fields beyond.

Another significant modification was the addition of Solatube skylights in the ceiling of the building so that during the day natural light can light the building entirely.

Pool in engineered building with skylights
Skylights were included to light the facilities during the day

Because of different energy requirements for the different activities, the complex was separated into two buildings, a swimming facility with 23,000 square feet (2,137 square metres) and one for basketball with 16,000 square feet (1,486 square metres) of space.

Pali said that the goal was to be able to get the basketball building as close to net-zero as possible.

Basketball court at Obama sports complex
Large glass windows open up to the exterior athletic fields

SPF Architects used the aforementioned skylights, photovoltaic panels and grey water re-collection to approach this goal, the success of which won't be known until the building has been used for some time, according to Pali.

Pali also cited the lightweight steel and efficiency of the PEMBs as sustainable aspects of the design.

Another aspect of the design built specifically for the arid environment was drought-resistant landscaping designed by Hood Design Studio.

According to SPF Architects, a grid-like pattern was used to incorporate five of the different ecologies of southern California to "physically tie the buildings and sports fields together while giving the community attractive and useable parkland in the voids between facilities".

Basketball court with skylights
The architects wanted the basketball court to achieve Net-Zero energy usage

The complex – well-known for being a place where tennis players Venus and Serena Williams practised as youths – opened in June 2022. The name change came after a local street was named for the former president.

SPF Architects has completed other projects in California including louvre-clad lofts in Hollywood and a three-winged hilltop residence in Bel Air.

The photography is by Mike Kelley


Project credits

Architect: Zoltan E. Pali, FAIA | SPF:architects
Landscape architect: Hood Design Studio
General contractor: Pinner Construction
Structural, plumbing and mechanical engineering: Buro Happold
Civil engineer: Tetra-Tech
Structural engineer: JCE Structural Engineering Group
Electrical engineer: V&M Electrical Engineering
Aquatic design: Aquatic Design Group